Industrial Production Line Intervention
- Year
- 2001
- Location
- Avilés, Asturias, Spain
- Status
- Completed
- Sector
- Industrial / Production Facility
- Scope
- Execution project, refurbishment project and site direction
Description
Technical intervention on an industrial production line in Avilés (Asturias) developed between 2001 and 2003. The brief covered execution-level documentation, refurbishment design for the existing production hall and full site direction during construction. Work included adaptation of the structural envelope to support new process equipment, reorganisation of production flows, upgrade of finishes and floors for industrial wear, and coordination with the mechanical, electrical and process disciplines. Construction was sequenced around the plant's production calendar to limit downtime. The project reinforced Locle Studio's specialisation in industrial process environments in northern Spain, combining architecture, refurbishment and on-site technical responsibility under a single design team.
Project Brief
2001 · Avilés, Asturias, SpainOverview
Refurbishment and execution project for an industrial production line in Avilés, integrating new process equipment into an active manufacturing facility.
Scope of Work
- 01Execution project documentation
- 02Production hall refurbishment design
- 03Structural adaptation for new process equipment
- 04Site direction during construction
- 05Multidisciplinary coordination (MEP and process)
Approach
Construction sequenced around the plant's production calendar, prioritising minimal downtime while reorganising flows and upgrading the industrial envelope.
Outcome
A modernised production hall ready for new equipment, with improved flows, finishes and structural performance.